Job type: DFE/Gas Open Fire
Project Length: 1 day
Completed by: Toast

Initial Situation:
Open gas fire on third floor of a Mayfair apartment, was leaking into the fourth floor apartment above.

Project Challenge:
FuranFLEX25 RWV Red liner had to be carried five floors to the roof and extra hose from boiler to fireplace had to be made due to the distance from ground floor to third floor apartment. Avoid disrupting the other residents.

Liner Chosen:
FuranFLEX25 RWV Red

Result:
No disruption to the other apartments in the same building. Due to the nature and value of these apartments no mess was created during the install.